Building the frames of the new rooms, based on the original 1908 built. Starting with the top floors.









Plumbing starting 5 April ’24






Isolation starting 16 April ’24



Followed by the gisping of the walls and ceiling






Building the frames of the new rooms, based on the original 1908 built. Starting with the top floors.









Plumbing starting 5 April ’24






Isolation starting 16 April ’24



Followed by the gisping of the walls and ceiling